Week 16
By Katie Black, 16 November 2011 –
During November the steel portal frame buildings for Units 3 and 2 have been erected and roofed. We hope to bring you up to date pictures very soon. Foundations are now being laid for the largest of the three external letting units, Unit 1, and next week the steelwork for that building will be erected. This week also saw the first foundations of the main mart building being poured, quite a milestone for us. The steelwork for the main building arrives at the end of November and so by Christmas all buildings will be erected; what a great Christmas present.